Letter from Committee Chair
To: The Board of Trustees and Residents of the Foothill-De Anza Community College District
The Citizens’ Bond Oversight Committee (the “Committee”) is pleased to present its annual report on the progress of the Foothill-De Anza Community College District’s two general obligation bond programs. In June 2006, the voters demonstrated their confidence in the district and passed Measure C, a $490.8 million general obligation bond initiative. In March 2020, the voters again supported the district by passing Measure G, an $898 million general obligation bond initiative. Measure C is nearing completion, with most projects finalized, while Measure G is gaining momentum with new initiatives underway. This annual report highlights Measure C’s financial activity and achievements alongside Measure G’s early progress and priorities.
The principal duties of the Committee include informing the public about the expenditure of Measure G and C bond proceeds; ensuring that the district spends bond money only for the purposes set forth in both measures; and producing an annual report of the Committee’s proceedings and activities, including a compliance statement. In contrast, the Board of Trustees’ fiduciary duties and responsibilities include but are not limited to monitoring the bond program, maintaining the list of authorized bond projects, prioritizing projects, and monitoring progress and authorizing spending on individual projects, and overseeing the annual performance and financial audits.
During the twelve months ending June 30, 2025 (fiscal year 2025), the district invested in two important projects using Measure C funds. At Foothill College, $1,099,511 was spent at the Sunnyvale Education Center to replace the HVAC system and to renovate classrooms. At De Anza College, $546,429 was spent to refresh furniture for students, faculty, staff and administrators.
During fiscal year (FY) 2025 the District continued spending on Measure G projects prioritized by the Board of Trustees. At De Anza College, $5,647,967 was spent on the Beach Volleyball project, which involves the renovation of the existing softball facility space into a six NCAA sized beach volleyball court facility to meet the college’s needs. The De Anza Event Center and Utility Relocation project had $6,210,399 of spending to include the planning for and relocation of existing utilities, demolition of Flint Center, and site preparations. At Foothill College, progress continued on the Pool and Physical Educational Facilities Improvements project, with $1,811,129 spent during the fiscal year. Additionally, $8,288,238 was spent on network upgrades and enhancements under Educational Technology Services.
Funding provided by our community through Measures G and C is an indispensable investment in supporting student success. Maintaining Foothill and De Anza colleges and the Sunnyvale Education Center as valuable community resources ensures that the district can continue to provide community members with affordable, quality education and training and retraining opportunities that lead to higher-paid higher-skilled jobs while meeting regional workforce needs.
The Citizens’ Bond Oversight Committee met four times during the fiscal year to review Measure G and C activities. At these meetings, district and program management staff provided the committee with written and oral reports and presentations, including:
- Measures G and C General Obligation Bond Program Planning Update
- Measure G Quarterly Detail Reports
- Measure C Quarterly Detail Reports
- Measure G Bond List Revision Reports
- Measure C Bond List Revision Reports
- Staff Reports
In addition to its meetings with the Foothill-De Anza staff to review Measures G and C spending, the Committee relied on the annual independent performance and financial audits conducted by Crowe, LLP (the “Auditor”) and an oral presentation by the Auditor to carry out its duties.
The Auditor concludes: "The results of our procedures indicated that, in all significant respects, Foothill-De Anza Community College District expended Measure C, June 2006 and Measure G, March 2020 General Obligation Bond funds for the year ended June 30, 2025 only for the specific projects developed by the District’s Board of Trustees and approved by the voters, in accordance with the requirements of Proposition 39, as specified by Section 1(b)(3)(C) of Article XIIIA of the California Constitution" (Performance Audit, page 1).
In conclusion, based on the meetings with and reports from staff, and the reports from the Auditor, the Committee concludes that, to the best of its knowledge, Measure G and C bond funds have been spent only on authorized Measure G and C bond projects developed by the District’s Board of Trustees and approved by the voters. The performance and financial audits can be viewed here.
Very truly yours,
Arthur Heinrich
Committee Chair
Committee Members
Citizens’ Bond Oversight Committee members are appointed by the Board of Trustees. The following members were active during the past fiscal year:
- Shyamoli Banerjee
Support Organization Representative - Nancy Bremeau
Business Organization Representative - Ty Conner
At-Large Representative - Arthur Heinrich
Senior Citizens’ Organization Representative - Bruce Tolley
At-Large Representative - Ellen Wheeler
Taxpayers Organization Representative
Committee Meetings
The committee meets on a quarterly basis, with meetings open to the public. For a listing of meetings and proceedings please visit the committee meeting page.
About Measure G
On March 3, 2020, voters in the district’s service area approved Measure G, a $898 million general obligation bond measure, enabling the district to:
- Upgrade facilities preparing students/veterans for university transfer and careers in fields such as healthcare, nursing, technology, engineering/sciences
- Upgrade and repair aging classrooms as well as labs for science, technology, engineering/math-related fields of instruction
- Acquire, construct, repair facilities, equipment and sites
Read the full Measure G Ballot Language here
About Measure C
On June 6, 2006, voters in the district’s service area approved Measure C, a $490.8 million general obligation bond measure, enabling the district to:
- Upgrade electrical, heating, ventilation, and fire/seismic safety systems
- Repair leaky roofs
- Improve access for people with disabilities
- Repair/expand classrooms for nurses/paramedics
- Upgrade technology
- Repair, construct, acquire, and equip buildings, classrooms, libraries, sites, science/computer labs
Measure G Bond Overview
as of June 30, 2025
| Location | Total Budget | Fiscal Year Expenditures |
Expenditures To Date |
Budget Remaining |
|---|---|---|---|---|
| Foothill College | $196,976,834 | $6,537,936 | $9,632,666 | $187,344,167 |
| De Anza College | $232,015,837 | $7,042,305 | $8,913,411 | $223,102,426 |
| De Anza Event Center | $27,576,352 | $6,210,399 | $9,528,440 | $18,047,911 |
| Central Services * | $20,146,840 | $962,243 | $1,110,684 | $19,036,155 |
| Educational Technology Services | $102,241,948 | $12,157,049 | $24,291,378 | $77,950,571 |
| District-Wide** | $67,792,319 | $1,868,607 | $29,783,825 | $38,008,494 |
| Employee and Student Housing | $200,689,910 | $1,056,122 | $1,056,122 | $199,633,788 |
| Overhead and Cost of Issuance | $37,968,603 | ($4,859,683) | $1,970,510 | $35,998,093 |
| Program Contingency | $20,353,000 | $0 | $0 | $20,353,000 |
| Unallocated Interest | $2,583,363 | $0 | $0 | $2,583,363 |
| Total: | $908,345,004 | $30,974,979 | $86,287,036 | $822,057,969 |
| Rounding factors may apply. Total budget includes interest received and accrued as of June 30, 2025 Source Documents: Quarterly Summary Report *Central Services = Projects that support instructional and student services district-wide. **District = Projects that support administrative operations and services district-wide. | ||||
Measure G Bond Objectives
The initial Measure G project list was defined by the Board of Trustees (November 2, 2020 Board Study Session) to meet specific bond objectives, summarized below:
- Accessibility: Upgrades and improvements to support accessibility (ADA) compliance.
- Infrastructure: Construction, improvements, and modernization of buildings, classrooms, technology, and equipment. Conservation upgrades to promote the use of clean renewable energy and reduce carbon footprint.
- Affordable Housing: Affordable Employee and Student housing options.
- Bond Support Projects to support the bond, including: campus and program contingency, refinancing outstanding lease obligations, and program management, cost of issuance, legal, planning, and assessment costs.
The following section highlights the top 5 Measure G projects that had activity during the fiscal year, and which bond objectives were supported.
Measure G Top 5 Projects by Fiscal Year Expenditures
- Educational Technology Services (ETS) - Network Upgrades and Enhancements - $8,288,238
Project Scope: Maintain and continuously upgrade the wired and wireless networks throughout the district to provide students, faculty, staff, and visitors with secure and robust Internet connectivity.
Bond Objective: Infrastructure, Accessibility
- De Anza Event Center and Utility Relocation - $6,210,399
Project Scope: Construction of new De Anza Event Center. This project to include the planning for and relocation of existing utilities, demolition of Flint Center, and site preparations.
Bond Objective: Infrastructure - De Anza College - Convert Existing Facility to Beach Volleyball - $5,647,967
Project Scope: Repurposing of the existing softball facility space into a six NCAA sized beach volleyball court facility to meet the users’ needs. The space will also include procurement and installation of required equipment, adjacent equipment storage and improvements to meet code requirements as necessary.
Bond Objective: Infrastructure
- Educational Technology Services (ETS) - Refresh Academic and Business Computer - $1,918,799
Project Scope: Provide students, faculty, and staff with advanced computing tools (i.e. desktops, laptops, tablets) for academic and business purposes.
Bond Objective: Infrastructure, Accessibility - Foothill College - Pool and Physical Educational Facilities Improvements - $1,811,129
Project Scope: Pool and Physical Education facilities improvements and modernization. Includes energy and water efficiency improvements, pool filtration, chemical treatment, lighting, locker rooms, and addition of gender neutral restrooms.
Bond Objective: Infrastructure
Note: Statements of project scope define the project for the total lifespan of each project respectively.
Measure G Bond Project List
as of June 30, 2025
| Project Name | Budget | Expenditures to Date | Budget Remaining |
|---|---|---|---|
| Foothill College | |||
| Board Approved* | |||
| Upgrade Natural Gas Service, Distribution and Electrification | $5,524,713 | $18,113 | $5,506,600 |
| Modernization Campus Wide Building Exteriors - Foothill | $27,623,264 | $90,564 | $27,532,700 |
| Modernize and Expand Student Success Centers | $2,762,356 | $9,056 | $2,753,300 |
| Improve Campus Wide Walk/Pathways for ADA Compliance | $11,427,265 | $37,465 | $11,389,800 |
| Swing Space | $1,381,128 | $4,528 | $1,376,600 |
| Renovate and Upgrade Existing Classroom Facilities | $1,657,434 | $5,434 | $1,652,000 |
| Campus Contingency (Foothill) | $6,602,602 | $0 | $6,602,602 |
| Active* | |||
| Renovate Football Stadium East Bleachers | $1,463,223 | $1,024,778 | $438,445 |
| Upgrade Infrastructure and HVAC Systems - Foothill | $53,972,383 | $1,382,758 | $52,589,625 |
| Upgrades to Campus Wide Electrical Systems | $13,813,171 | $62,545 | $13,750,627 |
| Upgrade Campus Site Access, Signage and Wayfinding | $15,908,472 | $362,739 | $15,545,733 |
| Upgrade Campus Wide Lighting for Safety and Energy Efficiency | $2,779,713 | $224,758 | $2,554,955 |
| Upgrade Campus Wide Building Management Systems | $2,081,471 | $128,327 | $1,953,144 |
| Sunnyvale Ed Center HVAC System Improvement and Classroom Renovation | $8,351,097 | $946,292 | $7,404,805 |
| Pool and Physical Educational Facilities Improvements | $16,753,238 | $2,282,633 | $14,470,605 |
| Renovate Dental Hygiene and Dental Assisting Facilities | $21,074,346 | $134,571 | $20,939,774 |
| Closeout* | |||
| Upgrade Restrooms to All Gender | $2,010,774 | $1,780,605 | $230,169 |
| Upgrade ADA Pathways at Buildings 8200 and 8600 | $1,790,183 | $1,137,500 | $652,684 |
| Consolidated* | |||
| Infrastructure and Distribution Piping Improvements Heating, Ventilation and Air Conditioning Upgrades Campus-wide | $0 | $0 | $0 |
| Foothill College Total: | $196,976,834 | $9,632,666 | $187,344,167 |
| De Anza College | |||
| Board Approved* | |||
| Pool and Physical Educational Quad Facilities Improvements | $4,766,921 | $15,629 | $4,751,292 |
| Site Improvements | $5,524,813 | $18,113 | $5,506,700 |
| Perimeter Campus Roadway, Pathway and Traffic Improvements | $6,906,042 | $22,642 | $6,883,400 |
| Signage and Wayfinding Improvements Campus-wide | $1,381,228 | $4,528 | $1,376,700 |
| Swing Space | $1,381,228 | $4,528 | $1,376,700 |
| Furniture, Fixtures and Equipment | $6,906,042 | $22,642 | $6,883,400 |
| Student Health Services Renovation | $2,071,792 | $6,792 | $2,065,000 |
| Physical Education Gymnasium Building Renovations | $377,839 | $1,239 | $376,600 |
| Automotive Technology Facilities Improvements and Modernization | $1,035,896 | $3,396 | $1,032,500 |
| Campus Contingency (De Anza) | $33,781,200 | $0 | $33,781,200 |
| Active* | |||
| Upgrade Fire Alarms and Suppression Systems | $4,849,755 | $208,556 | $4,641,200 |
| New Services for Students Building | $55,227,635 | $716,687 | $54,510,948 |
| Modernization Campus Wide Building Exteriors - De Anza | $18,243,235 | $475,200 | $17,768,035 |
| Convert Existing Facility to Beach Volleyball | $7,074,767 | $5,978,694 | $1,096,074 |
| Upgrade Infrastructure and HVAC Systems - De Anza | $34,587,038 | $820,713 | $33,766,325 |
| New Creative Arts Building | $39,832,887 | $159,186 | $39,673,701 |
| Upgrade S3, S7, and Seminar Flat Roofs | $2,508,294 | $9,099 | $2,499,195 |
| Modernize Building Interior and Exteriors | $2,109,878 | $8,922 | $2,100,956 |
| Renovate Restrooms in S2, S6 & L5 | $3,449,346 | $436,845 | $3,012,501 |
| Consolidated* | |||
| Infrastructure and Distribution Piping Improvements Heating, Ventilation and Air Conditioning Upgrades Campus-wide | $0 | $0 | $0 |
| Physical Plant replacement attached to Flint Center and Creative Arts Quad Buildings | $0 | $0 | $0 |
| De Anza College Total: | $232,015,837 | $8,913,411 | $223,102,426 |
| De Anza Event Center | |||
| Active* | |||
| De Anza Event Center and Utility Relocation | $27,576,352 | $9,528,440 | $18,047,911 |
| Consolidated* | |||
| De Anza Event Center and Utilities Relocation | $0 | $0 | $0 |
| Relocate Utilities DA Event Center | $0 | $0 | $0 |
| De Anza Event Center Total: | $27,576,352 | $9,528,440 | $18,047,911 |
| Central Services | |||
| Board Approved* | |||
| Central Services Contingency | $1,000,000 | $0 | $1,000,000 |
| Active* | |||
| Upgrade Security Systems | $13,057,228 | $222,547 | $12,834,681 |
| Construct New ETS Facilities for Permanent Storage and Processing | $3,016,394 | $90,969 | $2,925,425 |
| Acquire New Districtwide Vehicles | $3,073,218 | $797,169 | $2,276,049 |
| Central Services Total: | $20,146,840 | $1,110,684 | $19,036,155 |
| Educational Technology Services (ETS) | |||
| Board Approved* | |||
| Upgrades to Network Service Rooms | $11,346,901 | $37,201 | $11,309,700 |
| Educational Technology Services (ETS) Contingency | $5,000,000 | $0 | $5,000,000 |
| Active* | |||
| Upgrade Learning Space Tech - Foothill | $14,070,339 | $2,029,713 | $12,040,626 |
| Upgrade Learning Space Tech - De Anza | $14,165,474 | $1,803,228 | $12,362,246 |
| Upgrade Meeting Room Space Tech – Central Services | $822,530 | $152,446 | $670,085 |
| Refresh Academic and Business Computer | $26,963,414 | $6,144,231 | $20,819,183 |
| Server and Disk Storage Systems | $2,378,639 | $1,364,537 | $1,014,102 |
| Network Upgrades and Enhancements | $13,014,378 | $11,166,859 | $1,847,518 |
| IT Security Upgrades and Enhancements | $7,614,519 | $652,649 | $6,961,870 |
| Upgrade Voice Communication Systems | $3,810,134 | $362,053 | $3,448,081 |
| WIFI Expansion Project Phase 2 | $3,055,620 | $578,460 | $2,477,160 |
| Consolidated* | |||
| Learning Space Technology Upgrades and Enhancements | $0 | $0 | $0 |
| Assistive Listening Devices for Hearing Impaired Individuals | $0 | $0 | $0 |
| Educational Technology Services (ETS) Total: | $102,241,948 | $24,291,378 | $77,950,571 |
| District-Wide | |||
| Active* | |||
| Structural Upgrade Griffin House | $5,449,686 | $362,145 | $5,087,540 |
| Establish District-wide Energy and Sustainability Projects | $8,748,644 | $49,389 | $8,699,254 |
| Installation of EV Chargers | $4,065,058 | $658,166 | $3,406,892 |
| District-wide Contingency | $20,793,458 | $0 | $20,793,458 |
| Closeout* | |||
| Renovate Carriage House | $3,679,842 | $3,658,492 | $21,350 |
| Financially Complete* | |||
| Refinance Flint Center Parking Garage | $25,055,632 | $25,055,632 | $0 |
| District-Wide Total: | $67,792,319 | $29,783,825 | $38,008,494 |
| Affordable Employee and Student Housing | |||
| Active* | |||
| Establish Employee and Student Housing | $131,574,105 | $445,268 | $131,128,837 |
| Acquire Affordable Student Housing | $69,115,804 | $610,854 | $68,504,951 |
| Affordable Employee and Student Housing Total: | $200,689,910 | $1,056,122 | $199,633,788 |
| Overhead and Cost of Issuance | |||
| Active* | |||
| Program Overhead | $35,998,093 | $0 | $35,998,093 |
| Cost of Issuance | $1,970,510 | $1,970,510 | $0 |
| Overhead and Cost of Issuance Total: | $37,968,603 | $1,970,510 | $35,998,093 |
| Program Contingency | |||
| Board Approved* | |||
| Program Catastrophic Contingency | $20,353,000 | $0 | $20,353,000 |
| Program Contingency Total: | $20,353,000 | $0 | $20,353,000 |
| Unallocated Interest Earnings | |||
| Unallocated Interest Earnings | $2,583,363 | $0 | $2,583,363 |
| Unallocated Interest Earnings Total: | $2,583,363 | $0 | $2,583,363 |
| Measure G Total: | $908,345,004 | $86,287,036 | $822,057,969 |
Rounding factors may apply.
*Project Status Definitions:
Board Approved = Projects that have been approved by the Board of Trustees, but activity has not started yet.
Active = Project activity has started and is ongoing.
Closeout = Closure of project including providing final documents.
Consolidated = Budget and scope has merged with another project, and no budget or expenditures are remaining.
Financially Complete = No further financial activity.
Source Documents: Quarterly Detail Report
Measure C Bond Overview
as of June 30, 2025
| Location | Total Budget | Fiscal Year Expenditures |
Expenditures To Date |
Budget Remaining |
|---|---|---|---|---|
| Foothill College | $206,634,823 | $1,099,511 | $203,182,458 | $3,452,365 |
| De Anza College | $221,577,701 | $800,888 | $220,325,894 | $1,251,807 |
| District* | $100,342,093 | $7,638 | $97,799,122 | $2,542,971 |
| Total: | $528,554,617 | $1,908,037 | $521,307,474 | $7,247,143 |
| Rounding factors may apply. Total budget includes interest received and accrued as of June 30, 2025. Source Documents: Quarterly Summary Report *District = Projects that support information technology, administrative operations, and instructional services district-wide. Budget includes unallocated interest earnings. | ||||
Measure C Bond Project List
as of June 30, 2025
| Project Name | Budget | Expenditures To Date | Budget Remaining |
|---|---|---|---|
| Foothill College | |||
| Active* | |||
| Foothill Contingency | $0 | $0 | $0 |
| Sunnyvale Ed Center HVAC System Replacement and Classroom Renovation | $5,742,352 | $2,289,987 | $3,452,365 |
| Financially Complete* | |||
| Small Capital Repairs - Foothill | $3,811,411 | $3,811,411 | $0 |
| Building 1500 Renovation | $1,174,660 | $1,174,660 | $0 |
| PE Reroofing | $976,594 | $976,594 | $0 |
| Irrigation Pump Replacement | $258,260 | $258,260 | $0 |
| Building 2500 Reroof | $969,180 | $969,180 | $0 |
| Forum | $3,912,855 | $3,912,855 | $0 |
| Modernization of Learning Support Center, Biology and General Classrooms | $16,203,253 | $16,203,253 | $0 |
| Modernization of Building 5700 | $361,698 | $361,698 | $0 |
| Physical Education Lab Space | $1,512,408 | $1,512,408 | $0 |
| LA General Classrooms | $3,064,580 | $3,064,580 | $0 |
| Swing Space | $965,079 | $965,079 | $0 |
| Modernization of Administration Building & General Classrooms | $7,132,515 | $7,132,515 | $0 |
| Reconstruction of Stadium Bleachers & Press Box | $1,816,465 | $1,816,465 | $0 |
| Fine Arts Scene Shop | $767,347 | $767,347 | $0 |
| Japanese Cultural Center | $120,234 | $120,234 | $0 |
| Renovate Existing Footbridge | $253,693 | $253,693 | $0 |
| Storage Bldg at Swim Pool Area | $536,837 | $536,837 | $0 |
| Smithwick Theater | $4,139,185 | $4,139,185 | $0 |
| Library & ISC | $15,131,676 | $15,131,676 | $0 |
| Campus Wide Building System & Infrastructure Repairs/Upgrades | $620,727 | $620,727 | $0 |
| Mainline Irrigation - Phase II | $158,942 | $158,942 | $0 |
| Utility Lids - Phase II | $572,116 | $572,116 | $0 |
| Loop Road Resurfacing | $1,012,739 | $1,012,739 | $0 |
| Exterior Signage | $351,451 | $351,451 | $0 |
| Utility and Technology Infrastructure | $8,515,900 | $8,515,900 | $0 |
| Exterior Painting & Bird Remediation | $621,983 | $621,983 | $0 |
| Soccer and Softball Complex | $4,077,771 | $4,077,771 | $0 |
| Central Campus Site Improvements | $9,809,110 | $9,809,110 | $0 |
| Ornamental Horticulture & Veterinary Technology Demo. | $182,567 | $182,567 | $0 |
| Choral Rehearsal Hall | $150,002 | $150,002 | $0 |
| Dental Hygiene/Radiology Renovation | $254,814 | $254,814 | $0 |
| Install Photovoltaic Arrays - Campus Wide | $11,738,853 | $11,738,853 | $0 |
| Physical Sciences and Engineering Center | $57,627,320 | $57,627,320 | $0 |
| Group II Equip | $1,073,647 | $1,073,647 | $0 |
| Fire Alarm System Replacements Phase II | $1,576,697 | $1,576,697 | $0 |
| Parking and Circulation | $13,468,168 | $13,468,168 | $0 |
| Environmental Impact Report | $282,730 | $282,730 | $0 |
| Print Shop and Plant Services Facility | $287,833 | $287,833 | $0 |
| Fire Alarm System Replacement Phase III | $900,374 | $900,374 | $0 |
| Repair and Upgrade Miscellaneous Projects | $451,424 | $451,424 | $0 |
| Upgrade Doors and Hardware | $40,247 | $40,247 | $0 |
| Furniture and Equipment (Excluding Tech Related Equipment) Foothill | $11,705,554 | $11,705,554 | $0 |
| Outdoor and Indoor Student Seating (PSEC Café, 5000, 5100, 5400, etc.) | $13,440 | $13,440 | $0 |
| Faculty/Staff/Administrator Office Refresh (Furniture) | $15,311 | $15,311 | $0 |
| Classroom Furniture Replacement | $35,717 | $35,717 | $0 |
| Desktops | $6,447,933 | $6,447,933 | $0 |
| Printers | $82,325 | $82,325 | $0 |
| Refresh Multi Media Rooms | $1,152,489 | $1,152,489 | $0 |
| New Multi Media, Then Refresh | $4,039,132 | $4,039,132 | $0 |
| AV/Low Tech | $43,456 | $43,456 | $0 |
| Instructional Equipment for BH, FA & PE 18-19 | $146,942 | $146,942 | $0 |
| Consolidated* | |||
| Biology | $0 | $0 | $0 |
| Convert to Adaptive Learning Center | $0 | $0 | $0 |
| General Classrooms | $0 | $0 | $0 |
| Language Lab | $0 | $0 | $0 |
| General Classrooms | $0 | $0 | $0 |
| Lot 2 & 3 Security Improvements | $0 | $0 | $0 |
| Tennis Court Improvements | $0 | $0 | $0 |
| TV Center | $0 | $0 | $0 |
| Loop Road Lighting & Safety | $11,033 | $11,033 | $0 |
| ADA Transition Plan | $1,203 | $1,203 | $0 |
| Lot 4 | $0 | $0 | $0 |
| Lot 6 | $11,459 | $11,459 | $0 |
| Complete Lot 1H | $0 | $0 | $0 |
| Exterior Lighting | $0 | $0 | $0 |
| Campus Fountains | $0 | $0 | $0 |
| Replace Storm Drains | $0 | $0 | $0 |
| Tree Maintenance and Replacement | $0 | $0 | $0 |
| Slurry Coat and Re-stripe Lots 2 & 3 | $0 | $0 | $0 |
| Widen Access Road to PE | $0 | $0 | $0 |
| Replace Walkways | $106,320 | $106,320 | $0 |
| Veterinary Technology | $0 | $0 | $0 |
| Wireless Infrastructure | $0 | $0 | $0 |
| Pedestrian Bridge Lot 1 | $0 | $0 | $0 |
| LA Division Office /Classrooms | $9,816 | $9,816 | $0 |
| Loop Road Re-Alignment & Pedestrian Safety Improv | $186,997 | $186,997 | $0 |
| Expansion of VDI Servers | $0 | $0 | $0 |
| Computer Equipment (Carts, Monitors) | $0 | $0 | $0 |
| Accommodation/Ergonomic Furniture & Equipment (Staff, Faculty and Administrators) | $0 | $0 | $0 |
| Accessibility Project for Classrooms and Labs (Counters, Tables, Desks, Chairs) | $0 | $0 | $0 |
| Foothill College Total: | $206,634,823 | $203,182,458 | $3,452,365 |
| De Anza College | |||
| Active* | |||
| Upgrade Stadium and Track Visual Display | $430,622 | $82,781 | $347,841 |
| Upgrade Lighting at the Campus Center Building | $657,425 | $0 | $657,425 |
| De Anza Program Contingency | $200,003 | $0 | $200,003 |
| Student Lab ADA Accessibility Project | $11,651 | $11,651 | $0 |
| Furniture Refresh for Students, Faculty, Staff and Administrators | $3,447,598 | $3,447,598 | $0 |
| Outdoor Furniture Update and Refresh | $876,553 | $876,553 | $0 |
| System Wide Infrastructure | $404,797 | $404,797 | $0 |
| Closeout* | |||
| Upgrade Building E3 Design & Manufacturing Tech Labs | $1,750,383 | $1,703,845 | $46,538 |
| Financially Complete* | |||
| Small Capital Repairs - De Anza | $3,174,620 | $3,174,620 | $0 |
| L-7 | $3,805,020 | $3,805,020 | $0 |
| Baldwin Winery & East Cottage "Historic Renovation" | $6,159,985 | $6,159,985 | $0 |
| Seminar Building & Multicultural Center | $5,000,053 | $5,000,053 | $0 |
| Stadium and Track | $7,976,644 | $7,976,644 | $0 |
| L-Quad Seating | $158,918 | $158,918 | $0 |
| Corporation Yard | $4,008,793 | $4,008,793 | $0 |
| Signage (Phase I) | $671,069 | $671,069 | $0 |
| Library | $11,152,379 | $11,152,379 | $0 |
| Secured Bicycle Storage for Students | $227,117 | $227,117 | $0 |
| Signage and Wayfinding | $830,762 | $830,762 | $0 |
| Campus Site Lighting (Phase I) | $662,686 | $662,686 | $0 |
| Campus Wide Electronic Locks | $1,537,277 | $1,537,277 | $0 |
| Campus Wide Replacement/Repair of Interior and Exterior Finishes | $1,259,670 | $1,259,670 | $0 |
| Window Replacement Campus-wide | $405,845 | $405,845 | $0 |
| CDC Playground Maintenance & Shade Structure | $439,291 | $439,291 | $0 |
| Environmental Studies Area | $972,869 | $972,869 | $0 |
| Repair Tile Roofs | $5,293,951 | $5,293,951 | $0 |
| Flint Parking Structure Repairs | $6,946,144 | $6,946,144 | $0 |
| S2- S6 Phase II - Utility Master Plan - Phase I | $14,822,225 | $14,822,225 | $0 |
| ATC | $11,631,949 | $11,631,949 | $0 |
| G-Building | $962,243 | $962,243 | $0 |
| Campus Drive | $3,669,717 | $3,669,717 | $0 |
| Install Photovoltaic Arrays - Campus Wide | $11,732,597 | $11,732,597 | $0 |
| Elevator Upgrades - Campus Wide | $733,108 | $733,108 | $0 |
| ATC Central Plant Sound Attenuation | $686,818 | $686,818 | $0 |
| Auto Technology | $4,064,329 | $4,064,329 | $0 |
| Campus Center Phase II | $2,156,931 | $2,156,931 | $0 |
| Media & Learning Center | $49,972,863 | $49,972,863 | $0 |
| Group II Equip | $1,900,378 | $1,900,378 | $0 |
| Swing Space | $1,238,195 | $1,238,195 | $0 |
| Fire Alarm System Replacements Phase II | $284,997 | $284,997 | $0 |
| Forum | $2,155,798 | $2,155,798 | $0 |
| EIR | $43,233 | $43,233 | $0 |
| Roof and Trellis Repair: PE 1-2-6 & S7 - 8 | $1,562,017 | $1,562,017 | $0 |
| Combined Site Improvements | $8,580,539 | $8,580,539 | $0 |
| L-7 Phase II | $2,566,379 | $2,566,379 | $0 |
| Campus Exterior Lighting | $553,579 | $553,579 | $0 |
| Planetarium Roof Replacement | $84,340 | $84,340 | $0 |
| Interior and Exterior Improvements | $323,766 | $323,766 | $0 |
| Re-roof Science Buildings SC1 & SC2 | $1,466,401 | $1,466,401 | $0 |
| Campus Center Floors Improvement | $630,132 | $630,132 | $0 |
| Instructional Writing Surfaces Remediation | $224,292 | $224,292 | $0 |
| Furniture and Equipment (Excluding Tech Related Equipment) De Anza | $15,143,366 | $15,143,366 | $0 |
| Desktops | $9,495,622 | $9,495,622 | $0 |
| Printers | $210,759 | $210,759 | $0 |
| Refresh Multi Media Rooms | $3,889,795 | $3,889,795 | $0 |
| New Multi Media, Then Refresh | $2,102,269 | $2,102,269 | $0 |
| AV/Low Tech | $17,683 | $17,683 | $0 |
| Consolidated* | |||
| PE Quad Breezeway | $0 | $0 | $0 |
| Demolition of Staff House | $0 | $0 | $0 |
| Wireless Infrastructure- Phase II & III | $0 | $0 | $0 |
| Asphalt Walks | $0 | $0 | $0 |
| East Cottage "Historic Renovation" | $0 | $0 | $0 |
| Irrigation - Branches | $0 | $0 | $0 |
| Landscaping Phase II | $0 | $0 | $0 |
| Campus Exterior Lighting Phase II | $0 | $0 | $0 |
| Resurface Parking Lots E & I | $0 | $0 | $0 |
| Construct Parking Lot K | $0 | $0 | $0 |
| Sunken Garden | $0 | $0 | $0 |
| Slip Line Storm Drain Main Lines | $0 | $0 | $0 |
| Repair Stone Pavers in Court Yards | $0 | $0 | $0 |
| Slurry Seal Lots A, B, and Flint Center Parking Garage | $0 | $0 | $0 |
| L5 Central Plant | $0 | $0 | $0 |
| Baseball & Softball Fields | $0 | $0 | $0 |
| ADA Transition Plan | $0 | $0 | $0 |
| Construct New Covered Gathering Area | $0 | $0 | $0 |
| Financial Aid Outreach Office | $0 | $0 | $0 |
| Multicultural Center | $0 | $0 | $0 |
| Planetarium Expansion | $0 | $0 | $0 |
| Parking and Circulation | $0 | $0 | $0 |
| Cancelled* | |||
| A8 | $190,936 | $190,936 | $0 |
| Phase II - Renovation of A9 | $0 | $0 | $0 |
| Master Landscaping (Phase I) | $0 | $0 | $0 |
| Renovation of Admin. Phase II | $0 | $0 | $0 |
| Construct New Transit Center | $18,319 | $18,319 | $0 |
| De Anza College Total: | $221,577,701 | $220,325,894 | $1,251,807 |
| District (excluding technology projects) | |||
| Active* | |||
| District Program Contingency | $2,065,790 | $0 | $2,065,790 |
| Program Overhead | $158,511 | $0 | $158,511 |
| Financially Complete* | |||
| District Vehicles | $3,194,909 | $3,194,909 | $0 |
| Group II Equip | $522,600 | $522,600 | $0 |
| New District Offices | $22,288,808 | $22,288,808 | $0 |
| Pass through Account for OH Collection | $0 | $0 | $0 |
| Pass through Account for FET OH Collection | $0 | $0 | $0 |
| Catastrophic Contingency | $0 | $0 | $0 |
| Foothill-DeAnza Education Center | $41,031,817 | $41,031,817 | $0 |
| Cost of Issuance/Other | $1,801,622 | $1,801,622 | $0 |
| Consolidated* | |||
| Pay Off Existing Loan | $0 | $0 | $0 |
| Grounds and Landscaping | $0 | $0 | $0 |
| Repairs & Resurfacing of Roads & Parking | $0 | $0 | $0 |
| District Program Contingency - Property Acquisition | $0 | $0 | $0 |
| Pay Off Existing Debt | $0 | $0 | $0 |
| District (excluding technology projects) Total: | $71,064,057 | $68, 839,756 | $2,224,301 |
| Measure C ETS Projects (District Subcategory) | |||
| Active* | |||
| Upgrades to ETS Infrastructure | $151,714 | $7,638 | $144,076 |
| Financially Complete* | |||
| Phone Equipment | $2,297,540 | $2,297,540 | $0 |
| Network and Security | $4,722,637 | $4,722,637 | $0 |
| Consultants Spec Network Routers | $97,305 | $97,305 | $0 |
| Labor to Refresh Computers | $2,292,077 | $2,292,077 | $0 |
| Labor to Install Network Equipt/Routers etc | $510,094 | $510,094 | $0 |
| Replace ERP | $10,584,942 | $10,584,942 | $0 |
| ERP Hardware Refresh | $232,651 | $232,651 | $0 |
| Server Refresh | $1,994,653 | $1,994,653 | $0 |
| Server Growth | $211,002 | $211,002 | $0 |
| Wireless Infrastructure | $658,903 | $658,903 | $0 |
| Wireless Infrastructure - Phase II & III | $950,554 | $950,554 | $0 |
| ETS Facilities | $1,330,519 | $1,330,519 | $0 |
| Network Room Renovation | $1,864,314 | $1,864,314 | $0 |
| Desktops | $1,042,799 | $1,042,799 | $0 |
| Printers | $33,321 | $33,321 | $0 |
| Consolidated* | |||
| Data Center "C" | $128,415 | $128,415 | $0 |
| Measure C ETS Projects (District Subcategory) Total: | $29,103,440 | $28,959,364 | $144,076 |
| Unallocated Interest Earned | |||
| Unallocated Interest Earned | $174,594 | $0 | $174,594 |
| District Total: | $100,342,093 | $97,799,122 | $2,542,971 |
| Measure C Total: | $528,554,617 | $521,307,474 | $7,247,143 |
Rounding factors may apply.
Source Documents: Quarterly Summary Report
*Project Status Definitions:
Board Approved = Projects that have been approved by the Board of Trustees, but activity has not started yet.
Active = Project activity has started and is ongoing.
Closeout = Closure of project including providing final documents.
Financially Complete = Project has no further financial activity.
Consolidated = Budget and scope has merged with another project, and no budget or expenditures are remaining.
Cancelled = Budget moved to another project. No future activity expected.
Featured Projects
Projects that were active, completed, occupied or put in use this fiscal year.
De Anza College: Convert Existing Facility to Beach Volleyball


Measure G Budget: $7,074,767
Fiscal Year Expenses: $5,647,967
-
Completion date: September 2025
Project description: Repurposing of the existing softball facility space into a six NCAA sized beach volleyball court facility to meet the users’ needs. The space will also include procurement and installation of required equipment, adjacent equipment storage and improvements to meet code requirements as necessary.
Demolition of the Flint Center, Utilities, & Associated Work
Subproject of the De Anza Event Center and Utility Relocation project


-
Measure G Budget: $12,000,000
Fiscal Year Expenses: $5,263,571
-
Completion date: August 2025
Project description: The general scope of this subproject include the program and design for the demolition of the Flint Center, disconnection of associated utilities, and final site condition; assist with planning and coordination of relocation of current programs from buildings that will be impacted by demolition activities, as well as providing construction administration and close out.
Foothill College: Pool and Physical Educational Facilities Improvements


Measure G Budget: $16,753,238
Fiscal Year Expenses: $1,811,129
-
Completion date: January 2028
Project description: Pool and Physical Education facilities improvements and modernization. Includes energy and water efficiency improvements, pool filtration, chemical treatment, lighting, locker rooms, and addition of gender neutral restrooms.
Foothill College: Sunnyvale Center HVAC System Improvement and Classroom Renovation


Measure G Budget*: $8,351,097
Measure G Fiscal Year Expenses*: $946,292
Measure C Budget*: $5,742,352
Measure C Fiscal Year Expenses*: $1,099,511
Completion date: July 2026
- *This project is funded by both Measures G and C.
Project description: Replace existing mechanical system and modernize classrooms to house new programs (Respiratory Therapy & Radiologic Technology) that are currently at Foothill College that will be relocated to the Sunnyvale Education Center.
Measures G & C Side by Side
as of June 30, 2025
(from Financial Audit Report, page 4)
| Measure G | Measure C | |
|---|---|---|
| Revenues: | ||
| Interest and investment income | $4,968,006 | $323,965 |
| Expenditures: | ||
| Current: | ||
| Salaries | $848,221 | $18,286 |
| Benefits | $420,709 | $7,483 |
| Other services | $6,409,244 | $525,078 |
| Capital outlay | $23,296,805 | $1,351,190 |
| Total expenditures | $30,974,979 | $1,908,037 |
| Net change in fund balance | ($26,006,973) | ($1,584,072) |
| Fund balance, beginning of year | $145,064,942 | $8,831,214 |
| Fund balance, end of year | $119,057,969 | $7,247,142 |
From the Financial Audit Report, page 6, Note 1: The Measure C, June 2006 and Measure G, March 2020 fund is accounted for on a spending or “financial flow” measurement focus. This means that only current assets and current liabilities are generally included on the balance sheet. The reported fund balance is considered a measure of “available spendable resources.” Thus, the capital assets and long-term liabilities associated with the Bond Building Funds (Measure C, June 2006 and Measure G, March 2020) are accounted for in the basic financial statements of the District.