Letter from Committee Chair
To: The Board of Trustees and Residents of the Foothill-De Anza Community College District
The Citizens’ Bond Oversight Committee (the “Committee”) is pleased to present its annual report on the progress of the Foothill-De Anza Community College District’s two general obligation bond programs. In June 2006, the voters demonstrated their confidence in the district and passed Measure C, a $490.8 million general obligation bond initiative. In March 2020, the voters again supported the district by passing Measure G, an $898 million general obligation bond initiative.
The principal duties of the Committee include informing the public about the expenditure of Measure G and C bond proceeds; ensuring that the district spends bond money only for the purposes set forth in both measures; and producing an annual report of the Committee’s proceedings and activities, including a compliance statement. In contrast, the Board of Trustees’ responsibilities include but are not limited to overseeing the bond program, maintaining the list of authorized bond projects, prioritizing projects, and monitoring progress and spending on individual projects, and overseeing the annual performance and financial audits.
During the twelve months ending June 30, 2023 (FY 2023), the district invested in two important projects using Measure C funds. At De Anza College, $1,044,440 was spent to upgrade the Building E3 Design and Manufacturing Technologies Labs. At Foothill College, $255,322 was spent at the Sunnyvale Education Center to replace the HVAC system and to renovate classrooms.
During FY 2023 the District started spending on Measure G projects prioritized by the Board of Trustees. Just to name three examples, $1,911,946 was spent on educational technology services to refresh academic and business computer equipment (desktops, laptops, tablets) for students, faculty and staff. The District also spent $1,792,890 on network upgrades and enhancements to upgrade wired and wireless networks throughout the district. During FY 2023, the district has also started spending significant sums on district-wide program overhead adding up to $1,758,212. Such overhead spending included: management, cost of the bond issuance, legal fees, district office labor, program planning, and assessments.
Funding provided by our community through Measures G and C is an indispensable investment in supporting student success. Maintaining Foothill and De Anza colleges and the Sunnyvale Education Center as valuable community resources ensures that the district can continue to provide community members with affordable, quality education and training and retraining opportunities that lead to higher-paid higher-skilled jobs while meeting regional workforce needs.
The Citizens’ Bond Oversight Committee met four times during the fiscal year to review Measure G and C activities. At these meetings, district and program management staff provided the committee with written and oral reports and presentations, including:
- Measures G and C General Obligation Bond Program Planning Update
- Measure G Quarterly Summary Reports
- Measure C Quarterly Summary Reports
- Measure G Bond List Revision Reports
- Measure C Bond List Revision Reports
- Staff Reports
In addition to its meetings with the Foothill-De Anza staff to review Measures G and C spending, the Committee relied on the annual independent performance and financial audits conducted by Crowe, LLP (the “Auditor”) and an oral presentation by the Auditor to carry out its duties.
The Auditor concludes: "The results of our procedures indicated that, in all significant respects, Foothill-De Anza Community College District expended Measure C, June 2006 and Measure G, March 2020 General Obligation Bond funds for the year ended June 30, 2023 only for the specific projects developed by the District’s Board of Trustees and approved by the voters, in accordance with the requirements of Proposition 39, as specified by Section 1(b)(3)(C) of Article XIIIA of the California Constitution" (Performance Audit, page 5).
In conclusion, based on the meetings with and reports from staff, and the reports from the Auditor, the Committee concludes that, to the best of its knowledge, Measure G and C bond funds have been spent only on authorized Measure G and C bond projects developed by the District’s Board of Trustees and approved by the voters. The performance and financial audits can be viewed here.
Very truly yours,
Bruce Tolley
Committee Chair
Committee Members
Citizens’ Bond Oversight Committee members are appointed by the Board of Trustees. The following members were active during the past fiscal year:
- Joan Barram
Bona-fide Taxpayers Organization Representative - Nancy Bremeau
Business Organization Representative - Marge Bruno
Senior Citizens’ Organization Representative - Ty Conner
At-Large Representative - Amine Khechfé
Foothill-De Anza Support Organization Representative - Bruce Tolley
At-Large Representative
Committee Meetings
The committee meets on a quarterly basis, with meetings open to the public. For a listing of meetings and proceedings please visit the committee meeting page.
About Measure G
On March 3, 2020, voters in the district’s service area approved Measure G, a $898 million general obligation bond measure, enabling the district to:
- Upgrade facilities preparing students/veterans for university transfer and careers in fields such as healthcare, nursing, technology, engineering/sciences
- Upgrade and repair aging classrooms as well as labs for science, technology, engineering/math-related fields of instruction
- Acquire, construct, repair facilities, equipment and sites
Read the full Measure G Ballot Language here
About Measure C
On June 6, 2006, voters in the district’s service area approved Measure C, a $490.8 million general obligation bond measure, enabling the district to:
- Upgrade electrical, heating, ventilation, and fire/seismic safety systems
- Repair leaky roofs
- Improve access for people with disabilities
- Repair/expand classrooms for nurses/paramedics
- Upgrade technology
- Repair, construct, acquire, and equip buildings, classrooms, libraries, sites, science/computer labs
Measure G Bond Expenditures
as of June 30, 2023
| Location | Total Budget | Fiscal Year Expenditures |
Expenditures To Date |
Budget Remaining |
|---|---|---|---|---|
| Foothill College | $175,630,000 | $901,852 | $912,156 | $174,717,844 |
| De Anza College | $175,703,000 | $738,375 | $916,028 | $174,786,972 |
| De Anza Event Center | $101,728,800 | $401,248 | $935,787 | $100,793,013 |
| Central Services* | $20,000,000 | $13,024 | $13,024 | $19,986,976 |
| Educational Technology Services | $100,000,000 | $5,660,835 | $7,954,452 | $92,045,548 |
| District** | $327,613,451 | $1,928,352 | $29,713,627 | $297,899,824 |
| Total: | $900,675,251 | $9,643,686 | $40,445,074 | $860,230,177 |
| Rounding factors may apply. Total budget includes interest received and accrued as of June 30, 2023 Source Documents: Quarterly Summary Report *Central Services = Projects that support instructional and student services district-wide. **District = Projects that support employee and student housing, energy and sustainability, and administrative operations and services district-wide. District Budget includes unallocated interest earnings. | ||||
Measure G Top 5 Projects by Fiscal Year Expenditures
- Educational Technology Services (ETS) - Refresh Academic and Business Computer - $1,911,946
Project Scope: Provide students, faculty, and staff with advanced computing tools (i.e. desktops, laptops, tablets) for academic and business purposes.
- Educational Technology Services (ETS) - Network Upgrades and Enhancements - $1,792,890
Project Scope: Maintain and continuously upgrade the wired and wireless networks throughout the district to provide students, faculty, staff, and visitors with secure and robust Internet connectivity. - District-Wide - Program Overhead - $1,758,212
Project Scope: Program management, cost of issuance, legal, district office labor, program planning, and assessments.
- Educational Technology Services (ETS) - Server and Disk Storage Systems - $738,330
Project Scope: Equipment to provide remote, or virtualized, desktop applications to students, faculty, and staff for off-campus access to high-end software such as computer assisted design (CAD), video editing, and graphic design applications. - Educational Technology Services (ETS) - IT Security Upgrades and Enhancements - $526,800
Project Scope: Continuously upgrade network security systems to protect against cyber activity that could possibly compromise student, faculty, and staff accounts or district enterprise information systems.
Note: Statements of project scope define the project for the total lifespan of each project respectively.
Measure G Bond Project List
as of June 30, 2023
| Project Name | Budget | Expenditures to Date | Budget Remaining |
|---|---|---|---|
| Foothill College | |||
| Board Approved | |||
| Upgrade Natural Gas Service, Distribution and Electrification | $5,506,600 | $0 | $5,506,600 |
| Modernization Campus Wide Building Exteriors - FH | $27,532,700 | $0 | $27,532,700 |
| Modernize and Expand Student Success Centers | $2,753,300 | $0 | $2,753,300 |
| Upgrades to Campus Wide Electrical Systems | $13,766,500 | $0 | $13,766,500 |
| Improve Campus Wide Walk/Pathways for ADA Compliance | $12,389,800 | $0 | $12,389,800 |
| Upgrade Campus Site Access, Signage and Wayfinding | $15,831,400 | $0 | $15,831,400 |
| Upgrade Campus Wide Lighting for Safety and Energy Efficiency | $2,753,300 | $0 | $2,753,300 |
| Upgrade Campus Wide Building Management Systems | $2,064,900 | $0 | $2,064,900 |
| Swing Space | $1,376,600 | $0 | $1,376,600 |
| Renovate and Upgrade Existing Classroom Facilities | $1,652,000 | $0 | $1,652,000 |
| Campus Contingency (Foothill) | $8,059,905 | $0 | $8,059,905 |
| Active | |||
| Upgrade Restrooms to All Gender | $1,409,795 | $232,917 | $1,176,878 |
| Renovate Football Stadium East Bleachers | $1,376,600 | $168,546 | $1,208,054 |
| Improve ADA Pathways to Outdoor Classroom | $688,300 | $161,496 | $526,804 |
| Upgrade Infrastructure and HVAC Systems - FH | $61,948,700 | $16,480 | $61,932,220 |
| Pool and Physical Educational Facilities Improvements | $16,519,600 | $332,716 | $16,186,884 |
| Consolidated | |||
| Infrastructure and Distribution Piping Improvements Heating, Ventilation and Air Conditioning Upgrades Campus-wide | $0 | $0 | $0 |
| Foothill College Total: | $175,630,000 | $912,156 | $174,717,844 |
| De Anza College | |||
| Board Approved | |||
| Site Improvements | $5,506,700 | $0 | $5,506,700 |
| Perimeter Campus Roadway, Pathway and Traffic Improvements | $6,883,400 | $0 | $6,883,400 |
| Signage and Wayfinding Improvements Campus-wide | $1,376,700 | $0 | $1,376,700 |
| Swing Space | $1,376,700 | $0 | $1,376,700 |
| Furniture, Fixtures and Equipment | $6,883,400 | $0 | $6,883,400 |
| Student Health Services Renovation | $2,065,000 | $0 | $2,065,000 |
| Physical Education Gymnasium Building Renovations | $376,600 | $0 | $376,600 |
| Pool and Physical Educational Quad Facilities Improvements | $7,671,068 | $0 | $7,671,068 |
| Automotive Technology Facilities Improvements and Modernization | $1,032,500 | $0 | $1,032,500 |
| Campus Contingency (De Anza) | $8,781,200 | $0 | $8,781,200 |
| Active | |||
| Upgrade Fire Alarms and Suppression Systems | $4,818,400 | $110,607 | $4,707,793 |
| New Services for Students Building | $64,703,600 | $481,599 | $64,222,001 |
| Modernization Campus Wide Building Exteriors - DA | $20,650,100 | $28,667 | $20,621,433 |
| Convert Existing Facility to Beach Volleyball | $3,654,032 | $242,814 | $3,411,218 |
| Upgrade Infrastructure and HVAC Systems - DA | $34,416,900 | $27,818 | $34,389,082 |
| Modernize Building Interior and Exteriors | $4,006,700 | $1,844 | $4,004,856 |
| Renovate Restrooms in S2, S6 & L5 | $1,500,000 | $22,680 | $1,477,321 |
| Consolidated | |||
| Infrastructure and Distribution Piping Improvements Heating, Ventilation and Air Conditioning Upgrades Campus-wide | $0 | $0 | $0 |
| Physical Plant replacement attached to Flint Center and Creative Arts Quad Buildings | $0 | $0 | $0 |
| De Anza College Total: | $175,703,000 | $916,028 | $174,786,972 |
| De Anza Event Center | |||
| Active | |||
| De Anza Event Center and Utility Relocation | $101,728,800 | $935,787 | $100,793,013 |
| Consolidated | |||
| De Anza Event Center and Utilities Relocation | $0 | $0 | $0 |
| Relocate Utilities DA Event Center | $0 | $0 | $0 |
| De Anza Event Center Total: | $101,728,800 | $935,787 | $100,793,013 |
| Central Services | |||
| Board Approved | |||
| Equipment and Vehicles Acquisitions | $3,000,000 | $0 | $3,000,000 |
| Central Services Contingency | $1,000,000 | $0 | $1,000,000 |
| Active | |||
| Upgrade Security Systems | $13,000,000 | $6,628 | $12,993,372 |
| Construct New ETS Facilities for Permanent Storage and Processing | $3,000,000 | $6,396 | $2,993,604 |
| Central Services Total: | $20,000,000 | $13,024 | $19,986,976 |
| Educational Technology Services (ETS) | |||
| Board Approved | |||
| Upgrades to Network Service Rooms | $11,309,700 | $0 | $11,309,700 |
| Upgrade Voice Communication Systems | $3,769,600 | $0 | $3,769,600 |
| Educational Technology Services (ETS) Contingency | $5,000,000 | $0 | $5,000,000 |
| Active | |||
| Upgrade Learning Space Tech - FH | $13,865,081 | $276,653 | $13,588,428 |
| Upgrade Learning Space Tech - DA | $13,978,098 | $395,203 | $13,582,895 |
| Upgrade Meeting Room Space Tech - CS | $807,820 | $33,448 | $774,372 |
| Refresh Academic and Business Computer | $26,389,200 | $3,290,310 | $23,098,890 |
| Server and Disk Storage Systems | $2,262,000 | $741,200 | $1,520,800 |
| Network Upgrades and Enhancements | $12,079,300 | $2,680,035 | $9,399,265 |
| IT Security Upgrades and Enhancements | $7,539,200 | $526,800 | $7,012,400 |
| WIFI Expansion Project Phase 2 | $3,000,000 | $10,804 | $2,989,197 |
| Consolidated | |||
| Learning Space Technology Upgrades and Enhancements | $0 | $0 | $0 |
| Assistive Listening Devices for Hearing Impaired Individuals | $0 | $0 | $0 |
| Educational Technology Services (ETS) Total: | $100,000,000 | $7,954,452 | $92,045,548 |
| District | |||
| Board Approved | |||
| District-wide Energy and Sustainability Projects | $12,718,300 | $0 | $12,718,300 |
| Employee and Student Housing | $200,000,000 | $0 | $200,000,000 |
| Program Catastrophic Contingency | $20,353,000 | $0 | $20,353,000 |
| Active | |||
| Program Overhead | $43,621,938 | $2,699,119 | $40,922,819 |
| Renovate Carriage House | $3,175,252 | $266,202 | $2,909,050 |
| Structural Upgrade Griffin House | $5,444,200 | $314,612 | $5,129,588 |
| Cost of Issuance | $1,378,062 | $1,378,062 | $0 |
| District-wide Contingency | $15,288,516 | $0 | $15,288,516 |
| Financially Complete | |||
| Refinance Flint Center Parking Garage | $25,055,632 | $25,055,632 | $0 |
| Unallocated Interest Earnings | |||
| Unallocated Interest Earnings | $578,551 | $0 | $578,551 |
| District Total: | $327,613,451 | $29,713,627 | $297,899,824 |
| Measure G Total: | $900,675,251 | $40,445,074 | $860,230,177 |
Measure C Bond Expenditures
as of June 30, 2023
| Location | Total Budget | Fiscal Year Expenditures |
Expenditures To Date |
Budget Remaining |
|---|---|---|---|---|
| Foothill College | $206,590,891 | $255,322 | $201,147,793 | $5,443,098 |
| De Anza College | $221,536,551 | $1,566,581 | $218,507,218 | $3,029,333 |
| District* | $99,759,747 | $101,745 | $97,791,484 | $1,968,263 |
| Total: | $527,887,190 | $1,923,648 | $517,446,495 | $10,440,694 |
| Rounding factors may apply. Total budget includes interest received and accrued as of June 30, 2023. Source Documents: Quarterly Summary Report *District = Projects that support information technology, administrative operations, and instructional services district-wide. Budget includes unallocated interest earnings. | ||||
Measure C Top 5 Projects by Fiscal Year Expenditures
- De Anza College: Upgrade E3 Design & Manufacturing Tech Labs - $1,322,557
Project Scope: Reprogram the E3 building at De Anza College to meet the Design and Manufacturing Technologies End Users needs of expanding the lab use, incorporating the grant funded equipment into the space, and making the necessary improvements for the space. Additional scope includes LED lighting upgrades in the classroom and lab spaces.
- Foothill College: Sunnyvale Ed Center HVAC System Replacement and Classroom Renovation - $255,322
Project Scope: Replace the existing system with a new HVAC system including a new chiller, controls, and individual heating/cooling units in each classroom to supplement the HVAC system. Modernize classrooms to house new programs that are currently at Foothill College, but will be relocated to the Sunnyvale Ed Center. - De Anza College: System Wide Infrastructure - $123,605
Project Scope: Projects that provide campus-wide service and are an addition to the infrastructure provided for the support of students, staff and faculty, such as a key management system. The timeline is identified as needed projects are identified and implemented. - De Anza College: Furniture Refresh for Students, Faculty, Staff and Administrators - $116,842
Project Scope: Ongoing project to systematically refresh student, staff, faculty, and administrative offices and other student use spaces on campus. Furniture purchases include, but are not limited to: desks, tables, chairs and cabinets. The timeline is ongoing through the remaining life of the bond. - District: Wireless Infrastructure - Phase II & III - $74,443
Project Scope: Installation of campus-wide wireless internet access.
Measure C Bond Project List
as of June 30, 2023
| Project Name | Budget | Expenditures To Date | Budget Remaining |
|---|---|---|---|
| Foothill College | |||
| Board Approved | |||
| Sunnyvale Ed Center HVAC System Replacement and Classroom Renovation | $5,698,420 | $255,322 | $5,443,098 |
| Complete | |||
| Small Capital Repairs - Foothill | $3,811,411 | $3,811,411 | $0 |
| Building 1500 Renovation | $1,174,660 | $1,174,660 | $0 |
| PE Reroofing | $976,594 | $976,594 | $0 |
| Irrigation Pump Replacement | $258,260 | $258,260 | $0 |
| Building 2500 Reroof | $969,180 | $969,180 | $0 |
| Forum | $3,912,855 | $3,912,855 | $0 |
| Modernization of Learning Support Center, Biology and General Classrooms | $16,203,253 | $16,203,253 | $0 |
| Modernization of Building 5700 | $361,698 | $361,698 | $0 |
| Physical Education Lab Space | $1,512,408 | $1,512,408 | $0 |
| LA General Classrooms | $3,064,580 | $3,064,580 | $0 |
| Swing Space | $965,079 | $965,079 | $0 |
| Modernization of Administration Building & General Classrooms | $7,132,515 | $7,132,515 | $0 |
| Reconstruction of Stadium Bleachers & Press Box | $1,816,465 | $1,816,465 | $0 |
| Fine Arts Scene Shop | $767,347 | $767,347 | $0 |
| Japanese Cultural Center | $120,234 | $120,234 | $0 |
| Renovate Existing Footbridge | $253,693 | $253,693 | $0 |
| Storage Bldg at Swim Pool Area | $536,837 | $536,837 | $0 |
| Smithwick Theater | $4,139,185 | $4,139,185 | $0 |
| Library & ISC | $15,131,676 | $15,131,676 | $0 |
| Campus Wide Building System & Infrastructure Repairs/Upgrades | $620,727 | $620,727 | $0 |
| Mainline Irrigation - Phase II | $158,942 | $158,942 | $0 |
| Utility Lids - Phase II | $572,116 | $572,116 | $0 |
| Loop Road Resurfacing | $1,012,739 | $1,012,739 | $0 |
| Exterior Signage | $351,451 | $351,451 | $0 |
| Utility and Technology Infrastructure | $8,515,900 | $8,515,900 | $0 |
| Exterior Painting & Bird Remediation | $621,983 | $621,983 | $0 |
| Soccer and Softball Complex | $4,077,771 | $4,077,771 | $0 |
| Central Campus Site Improvements | $9,809,110 | $9,809,110 | $0 |
| Ornamental Horticulture & Veterinary Technology Demo. | $182,567 | $182,567 | $0 |
| Choral Rehearsal Hall | $150,002 | $150,002 | $0 |
| Dental Hygiene/Radiology Renovation | $254,814 | $254,814 | $0 |
| Install Photovoltaic Arrays - Campus Wide | $11,738,853 | $11,738,853 | $0 |
| Physical Sciences and Engineering Center | $57,627,320 | $57,627,320 | $0 |
| Group II Equip | $1,073,647 | $1,073,647 | $0 |
| Fire Alarm System Replacements Phase II | $1,576,697 | $1,576,697 | $0 |
| Parking and Circulation | $13,468,168 | $13,468,168 | $0 |
| Environmental Impact Report | $282,730 | $282,730 | $0 |
| Print Shop and Plant Services Facility | $287,833 | $287,833 | $0 |
| Fire Alarm System Replacement Phase III | $900,374 | $900,374 | $0 |
| Repair and Upgrade Miscellaneous Projects | $451,424 | $451,424 | $0 |
| Upgrade Doors and Hardware | $40,247 | $40,247 | $0 |
| Furniture and Equipment (Excluding Tech Related Equipment) Foothill | $11,705,554 | $11,705,554 | $0 |
| Outdoor and Indoor Student Seating (PSEC Café, 5000, 5100, 5400, etc.) | $13,440 | $13,440 | $0 |
| Faculty/Staff/Administrator Office Refresh (Furniture) | $15,311 | $15,311 | $0 |
| Classroom Furniture Replacement | $35,717 | $35,717 | $0 |
| Desktops | $6,447,933 | $6,447,933 | $0 |
| Printers | $82,325 | $82,325 | $0 |
| Refresh Multi Media Rooms | $1,152,489 | $1,152,489 | $0 |
| New Multi Media, Then Refresh | $4,039,132 | $4,039,132 | $0 |
| AV/Low Tech | $43,456 | $43,456 | $0 |
| Instructional Equipment for BH, FA & PE 18-19 | $146,942 | $146,942 | $0 |
| Consolidated | |||
| Biology | $0 | $0 | $0 |
| Convert to Adaptive Learning Center | $0 | $0 | $0 |
| General Classrooms | $0 | $0 | $0 |
| Language Lab | $0 | $0 | $0 |
| General Classrooms | $0 | $0 | $0 |
| Lot 2 & 3 Security Improvements | $0 | $0 | $0 |
| Tennis Court Improvements | $0 | $0 | $0 |
| TV Center | $0 | $0 | $0 |
| Loop Road Lighting & Safety | $11,033 | $11,033 | $0 |
| ADA Transition Plan | $1,203 | $1,203 | $0 |
| Lot 4 | $0 | $0 | $0 |
| Lot 6 | $11,459 | $11,459 | $0 |
| Complete Lot 1H | $0 | $0 | $0 |
| Exterior Lighting | $0 | $0 | $0 |
| Campus Fountains | $0 | $0 | $0 |
| Replace Storm Drains | $0 | $0 | $0 |
| Tree Maintenance and Replacement | $0 | $0 | $0 |
| Slurry Coat and Re-stripe Lots 2 & 3 | $0 | $0 | $0 |
| Widen Access Road to PE | $0 | $0 | $0 |
| Replace Walkways | $106,320 | $106,320 | $0 |
| Veterinary Technology | $0 | $0 | $0 |
| Wireless Infrastructure | $0 | $0 | $0 |
| Pedestrian Bridge Lot 1 | $0 | $0 | $0 |
| LA Division Office /Classrooms | $9,816 | $9,816 | $0 |
| Loop Road Re-Alignment & Pedestrian Safety Improv | $186,997 | $186,997 | $0 |
| Expansion of VDI Servers | $0 | $0 | $0 |
| Computer Equipment (Carts, Monitors) | $0 | $0 | $0 |
| Accommodation/Ergonomic Furniture & Equipment (Staff, Faculty and Administrators) | $0 | $0 | $0 |
| Accessibility Project for Classrooms and Labs (Counters, Tables, Desks, Chairs) | $0 | $0 | $0 |
| Contingency | |||
| Foothill Contingency | $0 | $0 | $0 |
| Foothill College Total: | $206,590,891 | $201,147,793 | $5,443,098 |
| De Anza College | |||
| Procurement | |||
| Student Lab ADA Accessibility Project | $211,653 | $11,651 | $200,003 |
| Furniture Refresh for Students, Faculty, Staff and Administrators | $3,647,295 | $2,592,041 | $1,055,254 |
| Outdoor Furniture Update and Refresh | $816,312 | $358,739 | $457,573 |
| System Wide Infrastructure | $647,333 | $291,861 | $355,472 |
| Construction | |||
| Upgrade E3 Design & Manf Tech Labs | $1,743,953 | $1,454,257 | $289,695 |
| Closeout | |||
| Desktops | $9,495,622 | $9,495,622 | $0 |
| Complete | |||
| Small Capital Repairs - De Anza | $3,174,620 | $3,174,620 | $0 |
| L-7 | $3,805,020 | $3,805,020 | $0 |
| Baldwin Winery & East Cottage "Historic Renovation" | $6,159,985 | $6,159,985 | $0 |
| Seminar Building & Multicultural Center | $5,000,053 | $5,000,053 | $0 |
| Stadium and Track | $7,976,644 | $7,976,644 | $0 |
| L-Quad Seating | $158,918 | $158,918 | $0 |
| Corporation Yard | $4,008,793 | $4,008,793 | $0 |
| Signage (Phase I) | $671,069 | $671,069 | $0 |
| Library | $11,152,379 | $11,152,379 | $0 |
| Secured Bicycle Storage for Students | $227,117 | $227,117 | $0 |
| Signage and Wayfinding | $830,762 | $830,762 | $0 |
| Campus Site Lighting (Phase I) | $662,686 | $662,686 | $0 |
| Campus Wide Electronic Locks | $1,537,277 | $1,537,277 | $0 |
| Campus Wide Replacement/Repair of Interior and Exterior Finishes | $1,259,670 | $1,259,670 | $0 |
| Window Replacement Campus-wide | $405,845 | $405,845 | $0 |
| CDC Playground Maintenance & Shade Structure | $439,291 | $439,291 | $0 |
| Environmental Studies Area | $972,869 | $972,869 | $0 |
| Repair Tile Roofs | $5,293,951 | $5,293,951 | $0 |
| Flint Parking Structure Repairs | $6,946,144 | $6,946,144 | $0 |
| S2- S6 Phase II - Utility Master Plan - Phase I | $14,822,225 | $14,822,225 | $0 |
| ATC | $11,631,949 | $11,631,949 | $0 |
| G-Building | $962,243 | $962,243 | $0 |
| Campus Drive | $3,669,717 | $3,669,717 | $0 |
| Install Photovoltaic Arrays - Campus Wide | $11,732,597 | $11,732,597 | $0 |
| Elevator Upgrades - Campus Wide | $733,108 | $733,108 | $0 |
| ATC Central Plant Sound Attenuation | $686,818 | $686,818 | $0 |
| Auto Technology | $4,064,329 | $4,064,329 | $0 |
| Campus Center Phase II | $2,156,931 | $2,156,931 | $0 |
| Media & Learning Center | $49,972,863 | $49,972,863 | $0 |
| Group II Equip | $1,900,378 | $1,900,378 | $0 |
| Swing Space | $1,238,195 | $1,238,195 | $0 |
| Fire Alarm System Replacements Phase II | $284,997 | $284,997 | $0 |
| Forum | $2,155,798 | $2,155,798 | $0 |
| EIR | $43,233 | $43,233 | $0 |
| Roof and Trellis Repair: PE 1-2-6 & S7 - 8 | $1,562,017 | $1,562,017 | $0 |
| Combined Site Improvements | $8,580,539 | $8,580,539 | $0 |
| L-7 Phase II | $2,566,379 | $2,566,379 | $0 |
| Campus Exterior Lighting | $553,579 | $553,579 | $0 |
| Planetarium Roof Replacement | $84,340 | $84,340 | $0 |
| Interior and Exterior Improvements | $323,766 | $323,766 | $0 |
| Re-roof Science Buildings SC1 & SC2 | $1,466,401 | $1,466,401 | $0 |
| Campus Center Floors Improvement | $630,132 | $630,132 | $0 |
| Instructional Writing Surfaces Remediation | $224,292 | $224,292 | $0 |
| Furniture and Equipment (Excluding Tech Related Equipment) De Anza | $15,143,366 | $15,143,366 | $0 |
| Printers | $210,759 | $210,759 | $0 |
| Refresh Multi Media Rooms | $3,889,795 | $3,889,795 | $0 |
| New Multi Media, Then Refresh | $2,102,269 | $2,102,269 | $0 |
| AV/Low Tech | $17,683 | $17,683 | $0 |
| Consolidated | |||
| PE Quad Breezeway | $0 | $0 | $0 |
| Demolition of Staff House | $0 | $0 | $0 |
| Wireless Infrastructure- Phase II & III | $0 | $0 | $0 |
| Asphalt Walks | $0 | $0 | $0 |
| East Cottage "Historic Renovation" | $0 | $0 | $0 |
| Irrigation - Branches | $0 | $0 | $0 |
| Landscaping Phase II | $0 | $0 | $0 |
| Campus Exterior Lighting Phase II | $0 | $0 | $0 |
| Resurface Parking Lots E & I | $0 | $0 | $0 |
| Construct Parking Lot K | $0 | $0 | $0 |
| Sunken Garden | $0 | $0 | $0 |
| Slip Line Storm Drain Main Lines | $0 | $0 | $0 |
| Repair Stone Pavers in Court Yards | $0 | $0 | $0 |
| Slurry Seal Lots A, B, and Flint Center Parking Garage | $0 | $0 | $0 |
| L5 Central Plant | $0 | $0 | $0 |
| Baseball & Softball Fields | $0 | $0 | $0 |
| ADA Transition Plan | $0 | $0 | $0 |
| Construct New Covered Gathering Area | $0 | $0 | $0 |
| Financial Aid Outreach Office | $0 | $0 | $0 |
| Multicultural Center | $0 | $0 | $0 |
| Planetarium Expansion | $0 | $0 | $0 |
| Parking and Circulation | $0 | $0 | $0 |
| Cancelled | |||
| A8 | $190,936 | $190,936 | $0 |
| Phase II - Renovation of A9 | $0 | $0 | $0 |
| Master Landscaping (Phase I) | $0 | $0 | $0 |
| Renovation of Admin. Phase II | $0 | $0 | $0 |
| Construct New Transit Center | $18,319 | $18,319 | $0 |
| Contingency | |||
| De Anza Program Contingency | $671,336 | $0 | $671,336 |
| De Anza College Total: | $221,536,551 | $218,507,218 | $3,029,333 |
| District (excluding technology projects) | |||
| Complete | |||
| District Vehicles | $3,194,909 | $3,194,909 | $0 |
| Group II Equip | $522,600 | $522,600 | $0 |
| New District Offices | $22,288,808 | $22,288,808 | $0 |
| Foothill-DeAnza Education Center | $41,031,817 | $41,031,817 | $0 |
| Consolidated | |||
| Pay Off Existing Loan | $0 | $0 | $0 |
| Grounds and Landscaping | $0 | $0 | $0 |
| Repairs & Resurfacing of Roads & Parking | $0 | $0 | $0 |
| District Program Contingency - Property Acquisition | $0 | $0 | $0 |
| Pay Off Existing Debt | $0 | $0 | $0 |
| Program Overhead and Other | |||
| Pass through Account for OH Collection | $0 | $0 | $0 |
| Pass through Account for FET OH Collection | $0 | $0 | $0 |
| Program Overhead | $243,741 | $0 | $243,741 |
| Cost of Issuance/Other | $1,801,622 | $1,801,622 | $0 |
| Unallocated Interest Earnings | $89,533 | $0 | $89,533 |
| Whole Program Contingency | |||
| District Program Contingency | $1,483,423 | $0 | $1,483,423 |
| Catastrophic Contingency | $0 | $0 | $0 |
| District (excluding technology projects) Total: | $68,839,756 | $70,412,712 | $1,816,697 |
| Measure C ETS Projects (District Subcategory) | |||
| Procurement | |||
| Server Growth | $219,795 | $211,002 | $8,793 |
| Wireless Infrastructure - Phase II & III | $962,702 | $950,554 | $12,148 |
| Closeout | |||
| ETS Facilities | $1,461,144 | $1,330,519 | $130,625 |
| Desktops | $1,042,799 | $1,042,799 | $0 |
| Complete | |||
| Phone Equipment | $2,297,540 | $2,297,540 | $0 |
| Network and Security | $4,722,637 | $4,722,637 | $0 |
| Consultants Spec Network Routers | $97,305 | $97,305 | $0 |
| Labor to Refresh Computers | $2,292,077 | $2,292,077 | $0 |
| Labor to Install Network Equipt/Routers etc | $510,094 | $510,094 | $0 |
| Replace ERP | $10,584,942 | $10,584,942 | $0 |
| ERP Hardware Refresh | $232,651 | $232,651 | $0 |
| Server Refresh | $1,994,653 | $1,994,653 | $0 |
| Wireless Infrastructure | $658,903 | $658,903 | $0 |
| Network Room Renovation | $1,864,314 | $1,864,314 | $0 |
| Printers | $33,321 | $33,321 | $0 |
| Consolidated | |||
| Data Center "C" | $128,415 | $128,415 | $0 |
| Measure C ETS Projects (District Subcategory) Total: | $29,103,292 | $28,951,726 | $151,565 |
| District Total: | $99,759,747 | $97,791,484 | $1,968,263 |
| Measure C Total: | $527,887,190 | $517,446,495 | $10,4440,694 |
Featured Projects
Completed, occupied or put in use this fiscal year
Refresh Academic and Business Computer

Educational Technology Services (ETS)
-
Measure G Budget: $26,389,200
Fiscal Year Expenses: $1,911,946
-
Completion date: December 2036
Project description: Provide students, faculty, and staff with advanced computing tools (i.e. desktops, laptops, tablets) for academic and business purposes.
Network Upgrades and Enhancements

Educational Technology Services (ETS)
Measure G Budget: $12,079,300
Fiscal Year Expenses: $1,792,890
-
Completion date: January 2027
Project description: Maintain and continuously upgrade the wired and wireless networks throughout the district to provide students, faculty, staff, and visitors with secure and robust Internet connectivity.
Measures G & C Side by Side
as of June 30, 2023
Total Expenditures vs. Budget remaining
Total Expenditures vs. Budget remaining
(from Financial Audit Report, page 4)
| Measure G | Measure C | |
|---|---|---|
| Revenues: | ||
| Interest and investment income | $1,886,343 | $286,294 |
| Expenditures: | ||
| Current: | ||
| Salaries | $340,000 | $107,473 |
| Benefits | $139,213 | $51,750 |
| Other services | $3,617,831 | $413,345 |
| Capital outlay | $5,546,642 | $1,351,080 |
| Total expenditures | $9,643,686 | $1,923,648 |
| Net change in fund balance | ($7,757,343) | ($1,637,354) |
| Fund balance, beginning of year | $79,987,521 | $12,078,047 |
| Fund balance, end of year | $72,230,178 | $10,440,693 |